Archipelago 3-Year Project Plan
Version: 1.0 Period: March 2026 -- March 2029 Goal: Production-ready Bitcoin Node OS with zero issues for end users Visual constraint: NEVER change animations, user experience, or visuals -- only neater layouts where highlighted
Current Status: Year 1, Q1, Sprint 1 (Starting)
Year 1: Foundation & Core Functionality (March 2026 -- February 2027)
Q1 2026 (March -- May): Fix Broken UI, Testing Infrastructure, Networking
Sprint 1: Test Infrastructure (Week 1-2)
- Install Vitest and configure frontend test runner
- Create first frontend unit tests: RPC client (8+ test cases)
- Create frontend unit tests: app store (6+ test cases)
- Create frontend unit tests: container store (5+ test cases)
- Create frontend unit tests: router guards (6+ test cases)
- Create backend integration test scaffolding
- Create backend unit tests: auth module (6+ test cases)
- Create backend unit tests: identity module (5+ test cases)
- Add CI-compatible test runner script (scripts/run-tests.sh)
Sprint 2: Fix Broken UI (Week 3-4)
- Fix Settings.vue: replace .path-option-card with .glass-card
- Fix Web5.vue top bar: verify glass sub-card consistency with Server.vue
- Remove duplicate network diagnostics from Settings.vue
- Server.vue: wire real RPC data to Local Network card
- Server.vue: wire real RPC data to Web3 card (show "Coming Soon")
Sprint 3: Backend Robustness (Week 5-6)
- Add system monitoring RPC endpoints (system.stats, system.processes, system.temperature)
- Add system monitoring to frontend Dashboard (CPU/RAM/Disk gauges)
- Add WiFi/Ethernet configuration RPC endpoints
- Add WiFi/Ethernet UI to Server.vue
- Implement CSRF protection on RPC layer
- Fix CORS policy: restrict to same-origin
- Add Nginx security headers
Sprint 4: Quality Baseline (Week 7-8)
- Run full sweep and record baseline in docs/quality-baseline.md
- Fix all silent catch blocks
- Remove all console.log in production paths
- Eliminate any-type usage in frontend
- Health-gated deploy: add pre-deploy health check
- Run canary deploy to secondary server
Q2 2026 (June -- August): DWN, Backup/Restore, Kiosk Mode, StartOS Independence
Sprint 5: DWN Protocol Implementation (Week 1-3)
- Implement DWN message store (dwn_store.rs)
- Implement DWN HTTP API (POST /dwn)
- Implement DWN peer sync protocol
- Add DWN management UI (DwnManager.vue)
- Add DWN RPC endpoints for protocol management
Sprint 6: Full Backup/Restore System (Week 4-5)
- Extend backup module for full system backup
- Add backup/restore RPC endpoints
- Add backup/restore UI to Settings
- Add backup to USB drive support
Sprint 7: Kiosk Mode Hardening (Week 6-7)
- Add kiosk mode crash recovery
- Add kiosk failsafe route (/recovery)
- Add kiosk-specific keyboard shortcuts
- Create kiosk systemd service
Sprint 8: StartOS Independence (Week 8-10)
- Audit StartOS code usage → docs/startos-dependency-audit.md
- Migrate essential StartOS utilities to archipelago
- Remove core/startos from workspace
- Run full regression test after removal
Q3 2026 (September -- November): App Integration, Auto-Updates, ARM64
Sprint 9: App Integration Testing (Week 1-3)
- Create app integration test suite (scripts/test-all-apps.sh)
- Fix all app integration failures
- Test dependency chains
- Test fresh install end-to-end
Sprint 10: Auto-Update System (Week 4-6)
- Implement update download and apply
- Add update notification to frontend
- Implement automatic update scheduling
- Create release manifest infrastructure
Sprint 11: ARM64 Support (Week 7-9)
- Set up ARM64 cross-compilation
- Test ARM64 container images
- Build ARM64 ISO
- Test ARM64 on Raspberry Pi 5
Sprint 12: Quality Hardening (Week 10-12)
- Achieve 50% frontend test coverage
- Achieve 50% backend test coverage
- Run overnight chaos test
- Run full quality sweep vs baseline
Q4 2026 (December -- February 2027): Security, Performance, Beta
Sprint 13: Security Hardening (Week 1-3)
- Implement session expiry and rotation
- Harden container security profiles
- Add secrets rotation mechanism
- Sanitize FileBrowser path traversal
- Remove FileBrowser token from URLs
- Run automated security scan
Sprint 14: Performance Optimization (Week 4-6)
- Profile and optimize backend startup (<3s)
- Optimize frontend bundle size (<500KB gzipped)
- Add WebSocket connection pooling and heartbeat
- Optimize container image pull performance
Sprint 15: Beta Release Prep (Week 7-10)
- Create comprehensive user documentation
- Create beta testing checklist
- Build and test beta ISO
- Publish v0.5.0-beta release
- Run 72-hour stability test
Year 2: Feature Completeness & Reliability (March 2027 -- February 2028)
Q1 2027 (March -- May): W3C DIDs, JSON-LD VCs, Hardware Wallet
Sprint 16: W3C-Compliant DIDs (Week 1-3)
- Implement W3C DID Document format
- Implement DID Document verification
- Update DID display in Web5.vue
- Add DID resolution across peers
Sprint 17: JSON-LD Verifiable Credentials (Week 4-6)
- Implement JSON-LD credential format
- Add credential presentation protocol
- Add credential management UI
Sprint 18: Hardware Wallet Integration (Week 7-10)
- Research and document hardware wallet integration
- Implement PSBT signing flow in LND RPC
- Add hardware wallet UI flow
- Add USB hardware wallet detection
Q2 2027 (June -- August): Multi-Node, VPN, Community Marketplace
Sprint 19: Multi-Node Orchestration (Week 1-4)
- Design multi-node architecture
- Implement node federation protocol
- Add multi-node dashboard
- Implement federated app deployment
Sprint 20: VPN and Mesh Networking (Week 5-8)
- Add Tailscale/WireGuard VPN integration
- Add VPN status to Server.vue
- Implement mesh networking discovery
- Add DNS-over-HTTPS configuration
Sprint 21: Community App Marketplace (Week 9-12)
- Design decentralized marketplace protocol
- Implement marketplace manifest discovery
- Implement app manifest publishing
- Add community marketplace tab to frontend
Q3 2027 (September -- November): Documentation, Reliability, Pre-Release
Sprint 22: Comprehensive Documentation (Week 1-3)
- Write developer documentation
- Write API documentation
- Write app developer SDK documentation
- Create Architecture Decision Records
Sprint 23: Reliability Engineering (Week 4-8)
- Implement graceful shutdown
- Add crash recovery
- Implement disk space management
- Add container health monitoring and auto-recovery
- Run 1-week continuous uptime test
Sprint 24: Pre-Release Quality (Week 9-12)
- Achieve 70% frontend test coverage
- Achieve 70% backend test coverage
- Run full regression screenshot comparison
- Publish v0.8.0-rc1 release candidate
Q4 2027 (December -- February 2028): Polish, Community, v0.9.0
Sprint 25: User Experience Polish (Week 1-4)
- Run complete UX audit
- Fix all UX audit findings
- Polish error handling across entire frontend
- Polish all forms
Sprint 26: Community Infrastructure (Week 5-8)
- Set up update server infrastructure
- Create community contribution guidelines
- Set up issue tracker and roadmap
- Publish v0.9.0 release
Year 3: Production Polish & Scale (March 2028 -- March 2029)
Q1 2028 (March -- May): Monitoring, Remote Management, Accessibility
Sprint 27: Advanced Monitoring (Week 1-4)
- Implement real-time metrics collection
- Add monitoring dashboard page
- Implement alerting system
- Add historical data export
Sprint 28: Remote Management (Week 5-8)
- Implement Tailscale-based remote access
- Add mobile-optimized remote management
- Implement remote notification system
Sprint 29: Accessibility and i18n (Week 9-12)
- Add ARIA labels and roles
- Add keyboard navigation testing
- Set up i18n infrastructure
Q2 2028 (June -- August): Pen Testing, Final QA
Sprint 30: Security Penetration Testing (Week 1-4)
- Run automated penetration test suite
- Manual security review of all RPC endpoints
- Harden Podman container isolation
- Add rate limiting to all sensitive endpoints
Sprint 31: End-to-End QA (Week 5-8)
- Create golden path test suite
- Run regression test across all hardware
- Achieve 80% test coverage
- Run 30-day soak test
Sprint 32: Documentation and Community (Week 9-12)
- Write troubleshooting guide
- Create walkthrough documentation
- Finalize all ADRs
- Publish v0.95.0-rc2
Q3 2028 (September -- November): v1.0 Release
Sprint 33: Final Polish (Week 1-4)
- Final UX audit
- Final security audit
- Final sweep
- Performance benchmark and optimize
Sprint 34: Release Engineering (Week 5-8)
- Create release automation
- Set up download/update infrastructure
- Write v1.0 release notes
- Build v1.0.0 release ISOs
Sprint 35: Launch (Week 9-12)
- Tag and publish v1.0.0
- Run 7-day post-release monitoring
- Create v1.1 roadmap
Q4 2028 (December -- February 2029): Maintenance
Sprint 36-39: Ongoing
- Monthly dependency update cycle
- Monthly security scan
- Quarterly quality sweep
- Community app reviews
- Plan v2.0 features
Milestone Summary
| Date | Milestone | Key Deliverables |
|---|---|---|
| May 2026 | Q1 Complete | Tests, UI fixes, security, quality baseline |
| Aug 2026 | Q2 Complete | DWN, backup/restore, kiosk, StartOS independence |
| Nov 2026 | Q3 Complete | App testing, auto-updates, ARM64 |
| Feb 2027 | v0.5.0-beta | First public beta |
| Nov 2027 | v0.8.0-rc1 | Release candidate |
| Feb 2028 | v0.9.0 | Pre-release |
| Nov 2028 | v1.0.0 | Production release |
Execution Method
- Execute via
/overnightskill — each session picks up next uncompleted tasks - Full detailed acceptance criteria in the original plan conversation
- Track progress by checking off items in this file as [x]