Release plan

Fixed scope

Retain all 48 requirement IDs: IndeeHub A01–A13 and platform B01–B10, C01–C10, D01–D11, E01–E04. The platform lane has 35 IDs and eight apps: KithMoot, Qortal, Podsteadr, Just Works, DATUM, Gashboard, Blossom and Public Web Router. App rows are acceptance obligations, not eight additional closed requirements. The inherited T00–T29 task map is a cross-lane work breakdown, not additional scope. See matrix.

Dependency order

  1. Reconcile provenance, requirements, existing dirty work and accepted component pins (T00); review shared contracts/risks (T01); establish reproducible artifacts and guarded delivery (T02).
  2. IndeeHub identity/Backstage/catalog precede authenticated checkout; checkout and recovery precede entitlement/player qualification. Publication must retain private-master and account isolation. First invoice, lost reply, withdrawal and restart must preserve one logical original operation.
  3. Connection UX precedes public files and private multi-file sharing. Cloud and native-identity dependencies remain separate from isolated provider fixtures.
  4. Finish coherent source/integration slices, mandatory regressions and independent review before package/installed acceptance. Test nonempty migration and rollback, not only fresh state.
  5. Freeze the integrated candidate (T22); qualify exact installed artifacts and operator scenarios (T23); hand off to the release owner (T24). B10 artwork remains the last feature-work correction after the other lanes; actual-device acceptance remains required before full closure. This does not impose a new blanket physical-acceptance prerequisite on independent source work.

Guarded delivery groups

Group Scope Required boundary
Y1 Identity/Backstage; diagnosed Mesh rendering slice only Provenance, contracts, artifact and applicable identity/asset tests
Y2 Publication/catalog/shared discussion Prior dependencies; separate public-event authority
Y3 Checkout/rentals/zaps/FIPS Financial/security review, recovery and explicit spend authority where needed
Y4 Chunked ecash/profits/durable update/availability Monetary preservation, budget and replica qualification
Y5 Cloud/connectivity/system/developer slices Slice-specific dependencies, not an unchecked omnibus
Y6 Radio/routes/sharing Hardware/network changes separately authorized
Y7 Background media and last artwork correction Actual supported devices
Final Frozen integrated backend/UI/apps/APK All mandatory gates and explicit operator/release-owner sign-off

Grouping is not deployment permission. Do not expose enabled mock payments or incompatible half-updated schemas. Blocked capacity/review/device dependencies block only dependent work, not all source implementation.

Timing and completion

Record attributable full-agent elapsed including investigation/failures separately from build/test runner duration and unknown queues. Use comparable qualified exits only; no historical countdown, human-hour multiplier or test-count percentage. External review, device, provenance and environment waits remain explicit. Completion requires the agreed installed/operator outcomes, not healthy containers or a green isolated suite.